Leadtimes depend on supplier strength

Our commercial HVAC product lead-times are all over the place. GRDs, terminal units and noise control from Price Industries had best in class lead-times, some under three weeks with quick ships in a day or two.

One of our five warehouses at ACI

Large rooftops, chillers and VFDs still have longer than normal lead-times. Electronic components stress the supply chain from our suppliers like Carrier, Yaskawa, and Johnson Controls. Commercial and industrial fans from Twin City and PennBarry are coming at industry leading lead-times.

The team at ACI has opted to stock more products and grow warehousing capabilities to buffer the negative impacts of long lead-times. A side bonus is our ability to stage large, complex projects in Portland and Seattle.